All information presented on this website (especially any do-it-yourself instructions) is given without any acceptance of liability for any damage or any injury howsoever caused.

Always consider your SAFETY FIRST!


Crankshaft

Making up the crank shaft

1st October 2010

I have decided that I will make up the crank shaft as the next part. This will be a fabricated crank using Loctite 603 high strength, oil tolerant retainer which can cope with a diametrical clearance up to 0.1 mm (about 0.003"), has a Service temperature range: -55°C to +150°C, and a Fixture time on steel of 8 minutes to join the various parts. To ensure that the Loctite 603 is fresh a new supply has been ordered.

A 7/8" mild steel bar was machined to diameters of 20mm at one end and 17mm the other. This was carried out by machining between centres so that the trueness of the machining was maintained.

The crank off set (web) will be drill and bored to fit the 20mm part of the shaft.
8th October 2010

Big end of crank

Another simple turing exercise. As the part will be fixed by Loctite 603 there are two grooves on each of the surfaces which will be located in the crank webs. The grooves enable a good spread of the Loctite to occur.

9th October 2010

The webs of the cranks were cut from bar that had been reduced from 12.7mm to 11mm as per the plans.

The holes to be a good snug fit on the big end and the main shaft were then machined. the two parts were locked together by a 4BA bolt through the centre of the web.

When the boring was complete a test assembly of the parts to ensure a good fit was tried. Then Loctite 603 was applied to one end of the big end and one of the mating faces of a web and allowed to set. Similarly one web was secured with Loctite 603 on the main shaft at the correct position from the reduced part.

The the two parts were introduced to each other and more Loctite applied to both parts and they were moved into place and then finally pinched home in the vice such was the fit.

The parts will be left, in the warmth of the house, for a minimum of 24 hours before the centre section of the main shaft is cut away to allow an sufficient time for 100% strength to be achieved.

10th October 2010

The centre of the crank was cut away and then the surplus filed flat.

Here the crank is set in the main bearings with bearing cap in place and the split bearing is set on the big end.

You can see that the harshness of the square corners has been removed and then may eventually be rounded even more.

17th October 2010

The splash guard was not included in the original kit of castings so this was purchased at the Midland Model Engineering Exhibition.

20th october 2010

I was able to collect my con rod based on the drawings but altered slightly so that copyright of the supplied plans was not breached, from the water jet cutters in Staplehurst.

The piece was originally 19mm thick so each side was milled 1.5mm all over and then to reduce the size further each side up to near the big by a further 2mm each side.

Here the con rod is being held to drill out the little end to size to take the bush.

Then drilling was carried out to provide the tapping holes for the studs to hold the big end together.

It was first drilled 5mm for the M6 tap and then 6.3mm to the half way mark for a clearance..

The con rod then had id marks centre popped on two sides and then cut in half. I am pleased to say that the big end bearing fit very well.

22nd October 2010

The big end stud holes were tapped  to take the M6.

The oilway to the bearing was drill and then counter drilled for tapping M4 for the oiler. The bearing was then cross drilled to meet the oil way.

New studs were made up as the big end is bigger on the rear side and than in the drawings.

The whole lot was assembled and tightened up and there is not a sign of binding.

The nuts are temporary as it needs to eb lock nutted with two nuts so these nuts will be cut down and another pair made.

12th November 2010

The crank now has had its keyway milled out. The way it was held is shown in the photo and is now completed.